Bulley & Andrews
Belden-Stratford restoration
Historic building restored while in use
Phone calls needed to schedule
The challenge
Restoring an occupied historic building meant coordinating deliveries through limited access points and elevators under tight logistics and COVID-19 restrictions. Whiteboards and Google Calendars gave no real-time visibility, causing conflicts and miscommunication.
The solution
Real-time scheduling let trades select their own time slots and coordinate shared resources, removing manual processes and the reliance on phone calls.
Implementation
The platform managed vehicles and elevator hoists as bookable resources while promoting collaboration between trades. Its interface let teams adapt schedules as circumstances changed.
The results
Delivery conflicts were minimised, scheduling phone calls dropped significantly, and visibility of the schedule created accountability that held through pandemic disruption.